B.H. Snell Hall Basement Classrooms Phase 2
| Project |
Schedule |
Budget |
Scope |
Last Update |
| CAMP/Rowley Lighting Upgrade |  |  |  | Jun 25, 2012 |
Time StatusJun 25, 2012: -> |
Budget StatusJun 25, 2012: -> |
Scope StatusJun 25, 2012: -> |
Construction StatusJun 25, 2012: -> |
|
| Student Center Patio |  |  |  | |
|
| Cheel Renovation - Coaches Offices and VIP Area |  |  |  | Sep 05, 2012 |
Time StatusSep 05, 2012: -> |
Budget StatusSep 05, 2012: -> |
Scope StatusSep 05, 2012: -> |
Construction StatusSep 05, 2012: -> |
|
| Clarkson Avenue Enhancement |  |  |  | Jul 25, 2011 |
Time StatusJul 25, 2011: -> |
|
| Center for Environment Display |  |  |  | Jul 08, 2011 |
Time StatusJul 08, 2011: -> |
|
| Clarkson Mausoleum |  |  |  | Jul 08, 2011 |
Time StatusJul 08, 2011: -> |
|
| Cadaver Lab in Clarkson Hall |  |  |  | Oct 26, 2011 |
Time StatusOct 26, 2011: -> |
Budget StatusOct 26, 2011: -> |
Scope StatusOct 26, 2011: -> |
Construction StatusOct 26, 2011: -> |
|
| Cheel Locker Room Renovations |  |  |  | Sep 13, 2011 |
Time StatusSep 13, 2011: -> |
Jul 25, 2011: -> |
Budget StatusSep 13, 2011: -> |
Sep 13, 2011: -> |
Scope StatusSep 13, 2011: -> |
Construction StatusSep 13, 2011: -> |
|
| CAMP 179 Renovation Upgrade |  |  |  | Sep 05, 2012 |
Time StatusSep 05, 2012: -> |
Budget StatusSep 05, 2012: -> |
Scope StatusSep 05, 2012: -> |
Construction StatusSep 05, 2012: -> |
|
| Shipley Center Renovation |  |  |  | |
|
| Clarkson University's Technology Advancement Center (TAC) |  |  |  | Jul 08, 2011 |
Time StatusJul 08, 2011: -> |
|
| Connections Sculpture |  |  |  | Sep 05, 2012 |
Time StatusSep 05, 2012: -> |
Budget StatusSep 05, 2012: -> |
Scope StatusSep 05, 2012: -> |
Construction StatusSep 05, 2012: -> |
|
| ERC Library 1st Floor, Student Affairs, Atrium Renovations |  |  |  | Jul 08, 2011 |
Time StatusJul 08, 2011: -> |
|
| Foster House |  |  |  | Jul 25, 2011 |
Time StatusJul 25, 2011: -> |
|
| Graham Hall Renovations |  |  |  | Jul 01, 2011 |
Budget StatusJul 01, 2011: -> Increase in asbestos abatement, stairs, and additional code requirements. We are also trying to fit in work in the basement. The additional approved scope has resulted in the increase. |
|
| Hantz Field |  |  |  | Jul 08, 2011 |
Time StatusJul 08, 2011: -> |
|
| Hamlin-Powers Center Core Stairway |  |  |  | Sep 05, 2012 |
Time StatusSep 05, 2012: -> |
Budget StatusSep 05, 2012: -> |
Scope StatusSep 05, 2012: -> |
Construction StatusSep 05, 2012: -> |
|
| Hamlin-Powers Fire Lane |  |  |  | Sep 05, 2012 |
Time StatusSep 05, 2012: -> |
Budget StatusSep 05, 2012: -> |
Scope StatusSep 05, 2012: -> |
Construction StatusSep 05, 2012: -> |
|
| Hamlin-Powers Old Health Center Renovation |  |  |  | Sep 13, 2011 |
Time StatusSep 13, 2011: -> |
Jul 01, 2011: -> The project is at risk because of the late start. This project will likely be at risk until it is delivered. |
Budget StatusSep 13, 2011: -> |
Scope StatusSep 13, 2011: -> |
Construction StatusSep 13, 2011: -> |
|
| Hamlin-Powers Parking Renovation |  |  |  | Sep 13, 2011 |
Time StatusSep 13, 2011: -> |
Jul 01, 2011: -> |
Budget StatusSep 13, 2011: -> |
Scope StatusSep 13, 2011: -> |
Construction StatusSep 13, 2011: -> |
|
| Hamlin-Powers 4th Floor Addition |  |  |  | Jul 08, 2011 |
Time StatusJul 08, 2011: -> |
|
| Hazardous Waste Building |  |  |  | Sep 05, 2012 |
Time StatusSep 05, 2012: -> |
Budget StatusSep 05, 2012: -> |
Scope StatusSep 05, 2012: -> |
Construction StatusSep 05, 2012: -> |
|
| Loop Road Asphalt Repair |  |  |  | |
|
| Main Entrance / New Parking Lot |  |  |  | Jul 25, 2011 |
Time StatusJul 25, 2011: -> |
|
| Moore House Center Core Renovation |  |  |  | Sep 05, 2012 |
Time StatusSep 05, 2012: -> |
Budget StatusSep 05, 2012: -> |
Scope StatusSep 05, 2012: -> |
Construction StatusSep 05, 2012: -> |
|
| Munter Walking Trails - Southern Racquette River Overlooks |  |  |  | Sep 05, 2012 |
Time StatusSep 05, 2012: -> |
Budget StatusSep 05, 2012: -> |
Scope StatusSep 05, 2012: -> |
Construction StatusSep 05, 2012: -> |
|
| Munter Walking Trails Along the Southern Raquette River |  |  |  | Jun 25, 2012 |
Time StatusJun 25, 2012: -> |
Budget StatusJun 25, 2012: -> |
Oct 27, 2011: -> Budget is on track. |
Jul 01, 2011: -> Funding will determine when overlooks, fine grading, and finishes can be applied. |
Scope StatusJun 25, 2012: -> |
Sep 13, 2011: -> |
Jul 01, 2011: -> A rough trail system will be in place by mid August. |
Construction StatusJun 25, 2012: -> |
|
| Nab Lab |  |  |  | Feb 15, 2012 |
Time StatusFeb 15, 2012: -> |
Budget StatusFeb 15, 2012: -> |
Scope StatusFeb 15, 2012: -> |
Sep 13, 2011: -> Issue has been resolved. |
Jul 25, 2011: -> Lighting order is delayed. We can install temporary lights. |
Construction StatusFeb 15, 2012: -> |
|
| Old Main East Wing |  |  |  | Jul 08, 2011 |
Time StatusJul 08, 2011: -> |
|
| Our Place Renovation |  |  |  | Sep 16, 2011 |
Time StatusSep 16, 2011: -> |
Budget StatusSep 16, 2011: -> |
Scope StatusSep 16, 2011: -> |
Construction StatusSep 16, 2011: -> |
|
| Peyton Hall-CITEC and McGrath |  |  |  | Sep 05, 2012 |
Time StatusSep 05, 2012: -> |
Budget StatusSep 05, 2012: -> |
Scope StatusSep 05, 2012: -> |
Construction StatusSep 05, 2012: -> |
|
| Peyton Hall Renovations |  |  |  | Jul 01, 2011 |
Time StatusJul 01, 2011: -> |
|
| Peyton 3rd Floor Wet Lab |  |  |  | Sep 05, 2012 |
Time StatusSep 05, 2012: -> |
Budget StatusSep 05, 2012: -> |
Scope StatusSep 05, 2012: -> |
Construction StatusSep 05, 2012: -> |
|
| Physical Plant Demolition |  |  |  | Jun 25, 2012 |
Time StatusJun 25, 2012: -> |
Budget StatusJun 25, 2012: -> |
Scope StatusJun 25, 2012: -> |
Construction StatusJun 25, 2012: -> |
|
| Price Hall First Floor Renovation and Exterior |  |  |  | Jun 25, 2012 |
Time StatusJun 25, 2012: -> |
Budget StatusJun 25, 2012: -> |
Scope StatusJun 25, 2012: -> |
Construction StatusJun 25, 2012: -> |
|
| Price Hall Second Floor Renovations |  |  |  | Feb 15, 2012 |
Time StatusFeb 15, 2012: -> |
Budget StatusFeb 15, 2012: -> No funding for any further external resource. |
Scope StatusFeb 15, 2012: -> |
Construction StatusFeb 15, 2012: -> |
|
| Quad Center Core AC Apartment |  |  |  | Sep 05, 2012 |
Time StatusSep 05, 2012: -> |
Budget StatusSep 05, 2012: -> |
Scope StatusSep 05, 2012: -> |
Construction StatusSep 05, 2012: -> |
|
| Quad 4th Floor Addition |  |  |  | Jul 08, 2011 |
Time StatusJul 08, 2011: -> |
|
| ROTC Rappel Tower |  |  |  | Sep 05, 2012 |
Time StatusSep 05, 2012: -> |
Budget StatusSep 05, 2012: -> |
Scope StatusSep 05, 2012: -> |
Construction StatusSep 05, 2012: -> |
|
| Rt. 11 Walking Path |  |  |  | Feb 07, 2012 |
Time StatusFeb 07, 2012: -> |
Budget StatusFeb 07, 2012: -> |
Scope StatusFeb 07, 2012: -> |
Construction StatusFeb 07, 2012: -> |
|
| Science Center Biotechnology Lab |  |  |  | Jul 25, 2011 |
Time StatusJul 25, 2011: -> |
|
| Science Center Lecture Hall 360 A/V Renovation |  |  |  | |
|
| Science Center Lighting Upgrade |  |  |  | |
|
| September 11th Memorial |  |  |  | Oct 27, 2011 |
Time StatusOct 27, 2011: -> |
Budget StatusOct 27, 2011: -> |
Scope StatusOct 27, 2011: -> |
Construction StatusOct 27, 2011: -> |
|
| Snell Baseball Field Construction |  |  |  | Mar 12, 2012 |
Time StatusMar 12, 2012: -> |
Budget StatusMar 12, 2012: -> |
Scope StatusMar 12, 2012: -> |
Construction StatusMar 12, 2012: -> |
|
| Snell Basement Digital Arts Classrooms |  |  |  | Jun 25, 2012 |
Time StatusJun 25, 2012: -> |
Budget StatusJun 25, 2012: -> |
Scope StatusJun 25, 2012: -> |
Construction StatusJun 25, 2012: -> |
|
| Snell Lighting Upgrade |  |  |  | |
|
| Structures Lab Renovation (for Wind Blade Testing) |  |  |  | Sep 05, 2012 |
Time StatusSep 05, 2012: -> |
Budget StatusSep 05, 2012: -> |
Scope StatusSep 05, 2012: -> |
Construction StatusSep 05, 2012: -> |
|
| Student Center |  |  |  | Jul 08, 2011 |
Time StatusJul 08, 2011: -> |
|
| TAC - Institute for a Sustainable Environment |  |  |  | Mar 01, 2012 |
Time StatusMar 01, 2012: -> |
Budget StatusMar 01, 2012: -> |
Scope StatusMar 01, 2012: -> |
Construction StatusMar 01, 2012: -> |
|
| Walker Arena / Locker Room |  |  |  | Jul 08, 2011 |
Time StatusJul 08, 2011: -> |
|
| Wilson RD Apartment |  |  |  | Sep 05, 2012 |
Time StatusSep 05, 2012: -> |
Budget StatusSep 05, 2012: -> |
Scope StatusSep 05, 2012: -> |
Construction StatusSep 05, 2012: -> |
|
| Woodstock Lodge Basement |  |  |  | Jul 08, 2011 |
Time StatusJul 08, 2011: -> |
|